Project characteristics

  • ID-RECCO ID
    169
  • Project status 2022
    Ongoing
  • Project name
    ‘El Arriero ’ Afforestation on degraded grasslands under extensive grazing
  • Secondary name
    ‘El Arriero ’ Afforestation on degraded grasslands
  • Country
    Uruguay
  • Last IDRECCO update year
    2020
  • Size (in hectare)
    5377
  • Start year
    ND
  • End year
    2109
  • Duration
    100
  • Project description
    The project comprises a total of 5,377 ha of land previously under extensive grazing by beef cattle, on which Afforestation for obtaining high-value, long-lived timber products and for sequestering large amounts of carbon dioxide from the atmosphere will be established. Plantation will be completed by year 2 of project and forests will be replanted after clear-cut harvest. Practices are certified with FSC standard. Planted forests will remove carbon dioxide from the atmosphere.
  • Objective 1
    timber production
  • Objective 2
    climate
  • Objective 3
    biodiversity conservation
  • Deforestation drivers
    cattle grazing, industrial agriculture or cattle ranching
  • Type of forest
    dry|humid
  • Project activity
    ARR
  • Project Type
    ARR
  • Details for Afforestation/Reforestation activity
    agroforestry, plantation
  • Multiple locations?
    Yes
  • Jurisdiction level 1
    Department : Treinta y Tres and Melo
  • Jurisdiction level 2
    Multiple locations

Carbon accounting

  • Crediting period
    2009-2109
  • Period to calculate annual carbon credits
  • Annual carbon credits
  • Total carbon credits
    1827052
  • Leakage is expected?
    no
  • Carbon pools included
    Above ground biomass | Below ground biomass | Dead wood | Litter | Soil organic carbon
  • Gasses included
    Other
  • Reference period start year
    ND
  • Reference period end year
    ND
  • Carbon standard 1
    VCS

Carbon certification

  • Carbon standard 1 Progress
    certified
  • Carbon standard 1 Publication date
    41288
  • Carbon standard 1 Weblinks
    https://registry.verra.org/mymodule/ProjectDoc/Project_ViewFile.asp?FileID=40241&IDKEY=lq934lkmsad39asjdkfj90qlkalsdkngaf98ulkandDfdvDdfh955492339
  • Carbon standard 1 Expiry date
    ND
  • Carbon standard 2
    none
  • Carbon standard 2 Progress
    ND
  • Carbon standard 2 Publication date
    ND
  • Carbon standard 2 Weblinks
    ND
  • Carbon standard 2 Expiry date
    ND
  • Carbon standard 3
    none
  • Carbon standard 3 Progress
    ND
  • Carbon standard 3 Publication date
    ND
  • Carbon standard 3 Weblinks
    ND
  • Carbon standard 3 Expiry date
    ND
  • Source of information
    https://registry.verra.org/app/projectDetail/VCS/961; https://vcsprojectdatabase2.apx.com/myModule/Interactive.asp?Tab=Projects&a=2&i=961&lat=-33.1000078887842&lon=-55.0250331826285&bp=1 (not accessible as of September 2020); https://registry.verra.org/app/projectDetail/VCS/961 (not accessible Aug2023)

Community level intervention

  • Any monetary benefits?
    Yes
  • Monetary benefit type
    Non-conditional
  • Monetary benefit detail
    Payment will be made through wage to the local employee
  • Provides employment?
    Yes
  • Are there non-cash benefits?
    Yes
  • Economic activities - type
    plantation forestry | tree planting
  • Is there tenure clarification?
    No
  • Is there environmental education?
    No
  • Is there forest access restriction or control/monitoring of deforestation?
    No
  • Is there forest enhancement?
    Yes
  • Is there community infrastracture improvement?
    ND
  • Is there other community benefits?
    ND